Public Meeting on Junction & Dehmel Water Main Project

The City of Frankenmuth will begin to replace the 20 inch water transmission main that runs along the south side of Junction Road. As part of this project, the 12 inch water main along Dehmel Road will also be replaced. This work is expected to begin on April 23, 2018. 

The City is inviting property owners and other interested parties to attend a project meeting on Tuesday, April 10 at 6 pm at City Hall. The meeting will last approximately one hour and will cover the following:
• Need for the project
• Construction timeline:
• Anticipated Start Date: April 23, 2018
• Substantial Completion Date: October 5, 2018
• Final Completion Date: November 2, 2018 

Potential Impact to Homeowners
• Project Working Hours
• Traffic Control
• Material/Equipment Storage
• Driveway Access/Driveway Reconstruction
• Mailboxes
• Black Dirt/Grass Seeding
• Night Connection Work
• Garbage and Mail Delivery
• Breaks